Product Burndown by Day


Report Description

This Day by Day version of the Product Burndown chart gives a view of how the team are performing on a daily basis. It also show how new work and bugs are adding to the total amount of work and hence whether the team will be able to complete by the intended Release date.

It is quite normal to see the Day by Day burdnown chart "Burnup" when:

  • New Product Backlog items are added
  • New Bugs are added
  • Existing Product backlog items are re-estimated

The trend line provides an indicator based on progress as to whether the team's velocity versus the rate at which work is added will deliver the desired features by the desired Release end date (based on the Sprints configured in the Release).

If the oustanding work is changed dramatically through a re-estimation or descoping exercise, then the Linear Regression line can provide an unduly optimistic or pessimistic prediction for completion time. This effect tends to even out over the passage of a number of Sprints.


Report Parameters

Parameter Description Default
Release View the burndown of the Product backlog for a specific Release or the whole project by either selecting the team project name or a specific release name. The current in progress Release
Team A multi-select dropdown providing the ability to filter the burndown data by a specific team or subset of teams The burndown across all Product Backlog items, including items assigned to specific teams and those that are unassigned
Adjustment By default this option sets the linear regression based trend line to run through the last real data point. If required this behaviour can be turned off by selecting "None", causing the trend line to be drawn as a best fit based on the available data points. Through Last Point


Screenshot