Product Cumulative Flow
Report Description
This report shows a cumulative view of the Product Backlog over time by state. Useful information shown by this chart:
- A view of how the total work to deliver a Release is changing over time
- The rate at which the team are completing the Product Backlog
- The amount of work In Progress at any time
It is quite common for teams to start many pieces of work and leave them "90% complete" in an un-testable state, rather than rapidly cycling work
from In Progress through to Done. This chart will surface this issue by showing a wide swath of In Progress work open at a single
point in time.
Report Parameters
| Parameter |
Description |
Default |
| Release |
View the Product Cumulative Flow chart for a specific Release or the whole
project by either selecting the team project name or a specific release name. |
The current in progress Release |
| Team |
A multi-select dropdown providing the ability to filter the backlog data by a specific team or subset of teams |
All backlog items, including those items assigned to specific teams and those that are unassigned |
| Weekends |
Selects whether weekends are included as valid working time or excluded from work time |
Excluded |
Screenshot